PGE to be compensated for Opole plant contracts termination
July 29, 2013   
Article's tools:
Print

Power utility PGE was granted a favorable court ruling over PLN 178.8 million in 2008 stranded costs tied to long-term contracts termination at the Opole power plant, PGE said in a market filing.

The total amount of contended compensations for termination of long-term contracts for 2008 amounts to PLN 434.7 million, the company said.